Meeting agenda:

  1. News & announcements.
  2. Activities on each instrument branch.
  3. FY2021 planning feedback.
  4. Closing remarks.

Discussion items

TimeItemWhoNotes

1. News & announcements

Everyone
  • First, we welcome Unknown User (aroy) to the TSO WG! She is an expert on exoplanet detection; she has focused a lot on actual instrument building and pipeline development. Very interested in exoplanet characterization, glad to be joining the TSO WG. 
  • Sarah Kendrew and Nestor Espinoza joining a meeting tomorrow about ground/detector testing. Objective is to understand all of the MIRI effects that will be paying attention to FY2021. 1 PM tomorrow, TSO WG members welcome to join!
20min

2. Activities on each instrument branch



  • NIRISS branch activities.  Currently work being focused on commissioning activities.


  • NIRSpec branch activitiesTony Keyes worked on updating the TSO Pipeline Testing Sheet. Some work done after the nominal deadline.


  • MIRI branch activities. Main activities related to pipeline testing. Currently post-deadline work, but still important to get done to identify bugs/optimize routines. Sarah Kendrew has also been taking a look at the NormalOPS data; this uses the OTB (the telescope simulator) to run realistic proposals, to check the entire system. Few TSO cases ran on the NormalOPS 9 run. Various problems; an imaging TSO didn't got processed, for instance. First test case of MRS-TSO shows some issues as well (ticket link). Sarah Kendrew encourages folks to check header keywords (at least for TSOs).


  • NIRCam branch activitiesBrian Brooks also took a look at NormalOPS 9 data (thanks Sarah Kendrew for the background info on getting the data for this!). Grism template TSO was successful; closely related to commissioning proposal (different target, smaller number of integrations). Were able to pull that; on a very quick review of the header keywords looked appropiate, but Nikolay Nikolov will have a deeper look. As for the comissioning analysis plans for TSO (CAP-33), the NIRCam team defined how to perform the analysis for the TSO target (an EB). Divided in two parts: (a) lower fidelity and (b) higher fidelity. Nikolay Nikolov mentioned that the idea is to run simulations through MIRAGE, and then run it through different pipelines (CalWebb, Nikolay's own pipeline, and the U. Arizona one).

  • In addition to the above, there is lab data with a mask in order to do analyses of GRISMR v/s GRISMC.

  • Also, Nikolay Nikolov currently looking at MIRAGE simulations and how do they change when you add more dark frames (currently 5, increased to 20). When re-running pipelines, same results on lightcurve scatter both from CalWebb and Nikolay's own pipeline.

  • Finally, Nikolay Nikolov also mentions trying to look back at the ramps-to-slopes (motivated by
    Jira
    serverSTScI JIRA
    serverIdaac911eb-9c55-3f14-8368-77b436fb6dc2
    keyJP-1667
    ). Would like to have an independent check with the Arizona pipeline.



Tony Keyes  mentions that apparently, there might be an issue with long TSO exposures, as they are not reported correctly by OSS (on the duration keyword). Apparently, the background resets not being included properly in the calculation. This is not an APT or ETC problem; the formula is correct, data being grabbed is OK. So probably an OSS issue. (https://jira.stsci.edu/browse/APT-87848), (meeting note Brian Brooks).

30min3. FY2021 planning feedback


Everyone




5min5. Closing remarks of the meeting


...