  • NIRISS: For the jump detection algorithm, the pipeline seems to be detecting a large fraction of jumps (~20% per integration). This is apparently a known issue in other instruments as well, and is due to aggresive parameters in the reference files. These will need to be calibrated with on-sky data.
  • NIRCam
  • MIRI:
  • NIRSpec:  The only NIRSpec Level 1 entry for DMS Build 7.5 is that all steps are verified to run without issues. We do NIRSpec does not have specific validation tests for level Level 1 as this pipeline is common to all instruments and there are several tests already included within the pipeline code that have been verified previously by the instrument teams.

Stage 2: Spectroscopic processing TSO testing

...