Time | Item | Who | Notes |
---|---|---|---|
5 mins | 1. News & announcements |
| |
10min | 2. Status on TSO commissioning papers | ||
NIRCam |
| ||
NIRISS | coming along, most content is there, still waiting on wavelength calibration and wavelength stability section. waiting on some input from Nestor. Most of the team is working on science observations with SOSS and some NIRSpec. It is snowing in Montreal.
| ||
NIRSpec |
| ||
MIRI |
| ||
Joint? |
| ||
5min | 3. TSO JDox discussion | Nestor Espinoza |
|
10min | 3. Instrument roundtable check-in | ||
NIRCam | looking into slope we see in flux - possibly related to observatory pitch angle? Action on Nestor Espinoza to discuss with mission office! | ||
NIRISS | had a meeting for analysis of LTT**** phase curve analysis. think there is a tilt event just at the time of the 2ndary eclipse. so it is important for data analysis. BB: having the discussion for NIRCam as well, how to notify the observers & what the impact is | ||
NIRSpec | a few issues with shorts but not affecting BOTS. BOTS all going well. | ||
MIRI |
| ||
2 mins | 4. Closing Remarks | meeting again in 2 weeks |